探花都是怎么认识女生的,呆哥,干柴烈火2免费观看电视剧

Sze Pak Tech Co., Ltd. injection mold maintenance plan!

datetime:2020-06-28 13:10:50 Visits:916 Source:思柏精密

In order to extend the service life of the company's injection molds, produce more products, and create greater economic benefits, the following maintenance plan is formulated:


1. Inspection and maintenance during mold installation


1. Clean the upper and lower surfaces of the injection mold before installing the mold to ensure that the installation surface of the injection mold and the worktable of the press are properly matched.


 2. After the mold is installed, the mold is opened, and the mold guide mechanism and the surface of the mold cavity are cleaned to ensure the quality of the manufactured parts.


3. Lubricate or apply grease to each sliding part of the mold.


4. Check and maintain the side guards, and clean the punching waste channels and holes.


5. Check the safety parts such as mold safety pins, safety screws, etc., find problems, and repair and replace them in time.


2. Maintenance during production


1. Regularly lubricate the press ring, rounded corners of the drawing die, the edge of the trimming die, and the part of the flanging knife block.


2. Regularly clean the waste channel of the small hole of the trimming punching die.


3. Often observe and feel the use state of the mold during production, if any abnormality is found, immediately shut down for inspection and eliminate it in time. After troubleshooting, proceed to production.



3. Maintenance after production


1. After the production is over, a comprehensive inspection of the injection mold is required.


2. Completely wipe the injection mold to clean up the waste and debris in the mold to ensure that there is no waste in the waste box.


3. Feedback the problems found in the use of injection molds truthfully, and make a record in the handover order or notify the repair personnel to carry out repairs.


Fourth, the first and second maintenance of the mold


1. The first-level maintenance of the mold is performed by the production operator. The main contents of maintenance are cleaning, lubrication and inspection.


2. The secondary maintenance work of the mold is completed by the mold repair personnel, and records are made according to the maintenance situation. Main contents of secondary maintenance:


a. Polish the rounded corners of the mold. If there are pressure pits, the mold should be polished.


b. Repair and restore the guiding parts found to be defective.


c. Repair welding and repair the die edge collapse and edge collapse during the use of the mold.


d. Replace damaged and invalid springs and other elastic parts (note the specifications and models of springs).


e. Replace the punch sleeve which is broken, bent, gnawed and damaged during use of the die.


f. Check whether the fastening parts are loose or damaged. If there is, replace it.


g. Check whether the pressure plate and discharge plate are damaged, and repair the damaged parts.


h. Check for leaks in the pneumatic system; if so, repair and replace.


5. Maintenance of injection mold for a long time


    For long-term injection molds, maintenance should be arranged every two months by opening the injection mold to remove dust and rust and oiling all parts of the injection mold.


请填写下方表单,我们会尽快与您联系
感谢您的咨询,我们会尽快给您回复!
主站蜘蛛池模板: 巧家县| 金山区| 昌黎县| 上杭县| 红河县| 万宁市| 永嘉县| 隆子县| 开封县| 肃南| 安乡县| 儋州市| 襄城县| 宁化县| 枞阳县| 静安区| 潞城市| 黑水县| 木兰县| 南充市| 鄂伦春自治旗| 百色市| 卢氏县| 确山县| 广南县| 云林县| 和田县| 历史| 石嘴山市| 库车县| 汾西县| 股票| 邢台县| 南木林县| 合江县| 信丰县| 正定县| 柳林县| 乌恰县| 长汀县| 元氏县|